Bidtally by Atesen Software

E-rate bid evaluation matrix: price as the primary factor

Last updated 30 October 2026 · for FY2027 applicants · Bidtally applies these rules in your browser

Every E-rate applicant that receives bids must evaluate them before selecting a provider, and the evaluation has to show that the price of the eligible products and services was the primary factor. The FCC rule (47 CFR 54.503(c)(2)(ii)(B)) says applicants may consider other relevant factors, but "price must be the primary factor considered". This page explains what that means in numbers, with USAC's own examples.

1. The weighting rule

2. USAC's example matrices

Example 1 factorWeightExample 2 factorWeight
Price of eligible products and services30%Price of eligible products and services50%
Prior experience25%Prior experience20%
Personnel qualifications20%Ineligible cost factors15%
Management capability15%Management capability10%
Environmental objectives10%Local vendor5%

Both are compliant: in example 1 price (30%) weighs more than prior experience (25%); in example 2 price (50%) weighs more than the ineligible cost factor (15%). USAC's multi-round example gives price 50 points in round 1 and 40 in round 2, 90 in all, more than any other factor.

3. How price points are usually computed

A common method gives the lowest qualified bid the full price weight and every other bid a share: price points = price weight × lowest eligible price ÷ this bid's eligible price. Other factors are scored on a fixed scale (for example 0–10) and weighted. In Bidtally's made-up sample, Valley Fiber bid $54,000 against a lowest qualified bid of $47,500: 30 × 47,500 ÷ 54,000 = 26.39 price points, and 82.89 points in total, the highest score, so it may win although it is not the cheapest.

4. The 28-day wait

You may not select a provider or sign a contract until at least 28 days after the Form 470 was certified (47 CFR 54.503(c)(4)); USAC publishes this as the allowable contract date. A new RFP document or an amendment restarts the 28 days, and a bid due date before the allowable contract date cuts the bidding window short.

5. Why it matters

In FY2025 USAC denied 370 funding requests from 205 applicants, worth $50.7 million before discounts, with reasons that cite the price factor, competitive bidding, the 28-day wait or the Form 470 (USAC FRN Status open data, read 30 October 2026). Keep the Form 470, the RFP, every bid, the scoring sheets and the contract for at least 10 years after the last day of service (47 CFR 54.516).

Check your own bids

Bidtally checks the weights, the 28-day wait and the selection, scores every bid and writes the memo you sign, in your browser. Try it free with the sample or see pricing.

Sources: eCFR title 47 part 54 (in force 1 October 2026); USAC, "How to construct an evaluation" (read 30 October 2026). Bidtally is independent software, not affiliated with USAC or the FCC.